MI-4B Maple Diversion Raw Water Relocation Completed
-- UPDATE --
January 1, 2023
The Phase MI-4B Raw Water Relocation Phase reached substantial completion in the summer of 2022. Phase MI-4B relocated raw water infrastructure to clear the path for Phase MI-4 Maple Diversion. The new 14” High Density Poly Ethylene (HDPE) pipe was operational in mid-June, and traffic control was removed. To allow the new raw water line to connect to the existing water infrastructure, modifications to the existing Well 8 pump house were also required. These improvements to the Well 8 pump house were also completed in June, and the final items were completed in August. It was a collective effort with Minot Parks and Recreation and other to complete this work on both sides of the river.